13 The major reason why a project manager would use written instead of oral communication is: A. documentationB. feedbackC. costD. barrier eliminationE. All of the above

题目

13 The major reason why a project manager would use written instead of oral communication is: A. documentation

B. feedback

C. cost

D. barrier elimination

E. All of the above

参考答案和解析
正确答案:A