54 You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?

A. Data item deliverables

B. Customer-furnished equipment and facilities

C. Long-lead procurement items

D. Customer-imposed milestones

E. Other subcontractor interface requirements